Solutions and Products
Guangda Electroplating
Scale:
0.4MW/0.8MWh
Location:
Taizhou·Linhai
Introduction: The project’s core functionality is arbitrage based on peak-to-valley price differences, optimizing electricity costs through two charging and two discharging cycles each day. It also implements demand-side management to precisely control the maximum power consumption, thereby reducing basic electricity charges. Meanwhile, the system can serve as a backup power source for critical equipment within the plant, enhancing the reliability of the production power supply. The commissioning of this project has brought direct economic benefits to Guangda Electroplating, effectively smoothing out electricity load fluctuations. It represents a successful demonstration of refined energy management using user-side energy storage in typical continuous-production industrial enterprises.